Eagle 25 Project Update

Eagle 25 Project Update

March 24, 2026
March 24, 2026
|
in
Blog Posts
|
by
Luke Munchrath

The Big Picture: AlcornConstruction’s Eagle 25 project is moving quickly from site prep into verticalconstruction, with favorable early spring weather helping crews stay on track.The project will encompass three commercial buildings totaling 608,412 squarefeet..

Where things stand:

  • Building 3: Earthwork and parking lots complete
  • Building 2: Grading underway, preparing for slabs
  • Safety: Nearly 60 days accident-free (since Alcorn     mobilized on the site)
  • Utilities: Staged and ready, waiting on permits.

 

What’s Happening now

Work is active across the site:

  • Roadwork and grading continue along Eagle Way Road
  • Crews are working efficiently to complete a temporary     Bull Canal crossing before the end-of-month deadline

By the numbers:

  • 36,000 cubic yards of dirt being moved
  • Large pipe installation underway for canal access

What’s Next

Construction is becoming visible:

  • First concrete pours for Building 3 are underway
  • Foundations will follow at ~400 linear feet/day
  • Mid-April: First slab pour (≈1,000 cubic yards each,     ~5 total pours)

The Bottom Line

If permits come through and the weathercooperates (which, in Colorado, is always a bit of a wildcard), the project isin a great position to stay on track.

Timeline: Still on track forJune 2027 completion.