Mikron’s Arapahoe County facility was a tight schedule success story. Working closely with the developer and design team, Alcorn expedited entitlement and design, resulting in approvals being received in only three months. Construction started in January, and although 20 of the first 40 working days were lost to weather, the project was delivered in the allotted nine month timeframe. Design assistance was provided on the elaborate electrical bus rail system, and cost option analysis facilitated an upgrade of the lighting to LED.